Maintenance can be performed by the operator’s own workshop rather than an outside contractor.
6.1 ADVANTAGES AND DISADVANTAGES
Advantages: closer control and flexibility; consistent standards; tighter cost control; better short-notice repair availability; own decisions on parts replacement.
Further advantages: no travel/time to an outside supplier; potentially lower costs because no external provider profit is paid; the workshop may become a profit centre.
Disadvantages: space/facilities are required; space could otherwise support other profit-making activity.
Disadvantages: increased capital outlay and overheads, specialist diagnostics/tools, extra staff recruitment/retention/training, and health, safety and legislative controls.
6.2 EQUIPMENT
Whether maintenance is in-house or contracted out, suitable premises/facilities, qualified staff and appropriate tools/equipment are required.
Typical in-house resources: undercover accommodation for the largest vehicle, suitable tools, hoists/pits, adequate lighting, a roller brake tester, headlamp alignment equipment and steam-cleaning facilities.
6.3 ORGANISATION AND PLANNING
Maintenance planning should be done well in advance so quality is maintained without harming operations.
Planning may use a wall chart or computer software.
Plans should cover inspection and servicing dates at least 6 months ahead.
Integrate annual test dates with servicing/inspection to avoid unnecessary duplication.
Review and update plans regularly and act on deviations.
Use a clear coding system to show programme components and progress.
6.4 CHANGES TO MAINTENANCE ARRANGEMENTS
Inspection intervals may be reduced without notification.
If increased beyond the interval specified on the operator licence, notify the Traffic Commissioner as soon as possible and within 28 days.
The same notification requirement applies when changing the maintenance provider.